By Stephen Greene –
November 24, 2026
The Department of Energy’s Office of Energy Dominance Financing (OEDF) has substantially accelerated its loan commitments in 2026, including making many that support nuclear energy. Just this year, OEDF has made commitments including (in rough chronological order):
• $26.5 billion to Southern Company for new gas-fired generation, nuclear uprates, energy storage, and transmission projects – the largest loan in the department’s history[1]
• A $17 billion conditional commitment for supply-chain loans[2] for ten new nuclear power projects
• $1.9 billion to restart the Duane Arnold nuclear plant
• $4.2 billion to Vistra for nuclear-plant modernization and 433 megawatts (MW) of uprates
• $5 billion to Constellation for 1,100 MW of uprates – with this loan, DOE says it has “identified” a total of 4.7 gigawatts of uprates[3] , or 95% of its goal of 5 gigawatts of uprates by 2029
• $5.1 billion to Alliant for new gas-fired generation, uprates to fossil-fired units, and gas storage
With all of this activity, OEDF is rapidly working through its available loan authority, which was $289 billion in early 2026[4], raising the prospect – which previously would have seemed unlikely – that additional authority may need to be considered.
New Nuclear Generation is Missing from OEDF’s Progress
The financial commitments to nuclear energy projects are clearly intended to support the goals established in the Executive Orders[5] related to nuclear energy. But one thing is missing – new nuclear generation. The Executive Order Reinvigorating the Nuclear Industrial Base[6] set a goal to have “10 new large reactors with complete designs under construction by 2030.” The conditional commitment for supply-chain loans is intended to facilitate that by restarting the supply chain and mitigating the risk that delays in long-lead components contribute to cost overruns. But so far, OEDF has been unable to obtain public commitments from project sponsors even for the supply-chain loans.
What appears to be holding up the sponsor commitments to new nuclear projects is the risk —and the perceived risk—of cost overruns. The perception that there is a high risk of cost overruns in nuclear energy projects is exacerbated by the experience building Vogtle units 3 and 4, the first new nuclear construction in decades. In hindsight, a substantial part of the apparent “overrun” may have been the result of underestimation in the initial effort to gain approval for the project, as DOE explained in its 2024 report, Pathways to Commercial Liftoff: Advanced Nuclear[7]. The report also laid out the steps to deliver new nuclear power plants on time and on budget.
Nonetheless, actions are needed to address the perception that the risk is still present. Managing this risk is primarily the responsibility of the project sponsor. However, the sponsors may need help—for example, investor-owned utilities appear to be concerned that taking on nuclear plant construction would affect their stock-price valuation due to the perception of risk on behalf of analysts and investors.
The risk is already substantially mitigated by investment tax credits, which offset up to 50 percent of actual project costs, including incurred budget overruns. Additional mitigation could be achieved by diversifying the risk through an agreement among multiple sponsors (the “order book” approach) or through government-funded or self-funded insurance approaches. Sponsors that are not sensitive to market perception – e.g., the Tennessee Valley Authority (TVA) or the New York Power Authority, could take on the first early mover projects, especially if they would receive the benefit of future learnings through future nuclear-power deployments.
While sponsors have the primary responsibility for managing cost risk, OEDF could help address the perception by sharing some of the risk with sponsors through more limited credit requirements to backstop loans, offsetting that with other risk-mitigation measures. These could include additional oversight (paid for by the borrower), increased credit fees (imposed by OEDF’s risk models), and by engaging its extensive technical and execution expertise and imposing process requirements, such as those gained through DOE’s
investigation of past projects, e.g., as described in Pathways to Commercial Liftoff.
A Wave of New Projects is Coming and Will Need Financing
DOE, including OEDF, appears to be primarily focused on traditional large light-water reactors like the Westinghouse AP1000. For example, the goal established in Reinvigorating the Nuclear Industrial Base is for “10 new large reactors” [emphasis added]. Yet new advanced reactor types, including those using non-light-water technologies, have recently made the most visible progress. Over the past two years, many new reactor technologies moved from “paper” to execution:
• Ontario’s Darlington SMR (GE Vernova Hitachi design) began construction in 2025 and earlier this year put its Basemat modular foundation in place[8]
• In April 2026, Kairos began construction[9] on its Hermes 2 power-generating demonstration project
• Also in April, TerraPower began construction[10] on its Natrium project in Kemmerer WY
• In September, TVA received a construction permit[11] for a GE Vernova Hitachi SMR, the first in the U.S.
• In November, the Long Mott Generating Station at Dow’s Seadrift TX plant received a construction permit[12] for an X-energy SMR; licensing was achieved on an 18-month schedule
• In addition, several microreactor technologies achieved milestones, including criticality testing, on accelerated timeframes
The projects currently in construction have financing in place, and some of the projects noted above may be ineligible for loan guarantees through OEDF (e.g., projects that have received other federal assistance such as through the Advanced Reactor Demonstration Program, or ARDP) or may have better alternative financing options. However, similar projects can be expected to follow them in short order and may seek OEDF financing.
These include, for example:
• The potential 320 MW Cascade Advanced Energy Facility[13] being developed by Energy Northwest, with support from Amazon, using X-energy’s technology
• Projects developed under the Master Plant Development Agreement[14] between Kairos Power and Google, which seeks to deploy a fleet of advanced nuclear power projects totaling 500 MW by 2035
OEDF needs to be prepared to finance projects such as these, which will be based on technologies with more limited deployment histories than conventional large light-water reactors, and are likely to seek non-recourse project structures. OEDF’s recent focus on conventional technologies, uprates, and balance-sheet-backed financings is admirable for its support for expanding energy resources, but it can’t be allowed to displace OEDF’s responsibility to support innovative technologies. OEDF’s original mission, still incorporated in its strategic plan[15], is to “boost American energy innovation [and] domestic technologies.” OEDF’s ability to participate in financing of projects relying on advanced nuclear energy technology also requires resources – adequate loan authority and credit subsidy appropriations[16], especially for Section 1703, as well as adequate funding for OEDF staff to support loan evaluations and ongoing monitoring.
Preparing for International Competition
The need to support advanced technologies being developed by U.S. companies is heightened because competitors are seeking to develop similar technologies – with government support. The European Union has a renewed focus on nuclear energy for energy security, and recently announced a strategy to bring European SMRs online[17] by the early 2030s. South Korea’s National Assembly passed the Special Act on the Promotion and Support of Small Modular Reactor Development[18] reflecting the view that SMRs will be needed for surging power demand and to manage carbon emissions. Most critically, multiple startups in China are pursuing SMRs[19] with the clear intent to pursue global deployment, backed by a robust supply chain and manufacturing base.
The U.S. must continue to provide the structures and resources to enable advanced nuclear energy projects to be financed and deployed. Doing so is essential not only for their value in providing reliable, clean energy for domestic growth and energy security, but also to maintain U.S. leadership in the international deployment of nuclear energy. A strong position in international deployment supports a valuable export market, U.S. geopolitical objectives (since nuclear energy projects lead to century-long relationships), and preserves U.S. influence regarding non-proliferation policies.
Conclusion
OEDF has substantially accelerated its loan commitments in 2026, including significant support for nuclear energy. However, firm commitments to new nuclear-energy projects are still missing from the portfolio, despite OEDF’s effort to stimulate such projects through its conditional commitment for supply-chain loans. Actual and perceived risks of cost overruns is holding back potential sponsors, and mechanisms to address cost risks are needed, including steps that could be taken by OEDF. Finally, OEDF needs to prepare for the impending challenge of financing advanced reactors using new reactor technologies— returning to its roots as the source of financing for innovative energy technologies. OEDF’s commitment to that role is needed to capture the benefits of new technology to help address domestic energy security, as well as to preserve U.S. global leadership in nuclear energy.
* * * * * The views expressed herein are solely those of the author and do not represent the views of any other organization or any government
Stephen Greene is a consultant, a nonresident senior fellow with the Atlantic Council’s Global Energy Center, and a senior fellow with the Nuclear Innovation Alliance. He was chief financial officer for Centrus Energy, a public company engaged in the sale of nuclear fuel and the development of nuclear enrichment technology. He led strategy for Progress Energy, an investor-owned electric utility, and served as practice-area leader for the consultant Pace Global Energy focused on energy markets and risk management. He arranged project financing for PG&E National Energy Group (US Generating Company), a leading independent-power developer and energy trader, and developed the company’s power market outlook to support project development.